Goodbye snow and hello spring from the Chesapeake Campus! There has been significant progress both inside and outside on the building since our last report in February.
The two-story North C wing is visible from the road and taking shape with the brick facade nearing completion, window installation, tile work, and painting underway. Drywall is being hung in the one-story South D wing while we complete the above ceiling rough-in of mechanical, electrical and plumbing. The A&B wings, which connect the C&D wing, are also in the framing and mechanical, electrical and plumbing rough-in phase. Within the next month, we will be starting on ceilings, elevator installation, exterior courtyard retaining walls, generator pad, and BGE permanent gas and power. We thank you for your incredible support and look forward to sharing further news in the coming weeks!